Wed Jul 22

Tour of Homes, July 25th-August 2nd

Pictures from the end of May to the completion of the home will debut after the Tour of Homes ends. Feel free to look at all photos to get an idea of what you can view in person starting July 25th!

Fri May 22
The 2-story rock wall on the house is almost complete.

The 2-story rock wall on the house is almost complete.

The stairs begin.

The stairs begin.

Front door trim is glued an nailed on.

Front door trim is glued an nailed on.

End of day, May 22nd.

End of day, May 22nd.

The rock wall on the lower level is getting close to complete. In the background, you can see the gravel pad for the future basketball court.

The rock wall on the lower level is getting close to complete. In the background, you can see the gravel pad for the future basketball court.

Thu May 21
John makes puts on the final details to the front door top before it goes up.

John makes puts on the final details to the front door top before it goes up.

The 7” white oak flooring starts in the kitchen.

The 7” white oak flooring starts in the kitchen.

The crown in the great room continues, meticulously. The radius was making my guys nervous. But, with an assist from the guys at Architectural Millwork, it was cut at the right angle and installed.

The crown in the great room continues, meticulously. The radius was making my guys nervous. But, with an assist from the guys at Architectural Millwork, it was cut at the right angle and installed.

Wed May 20
The back patios are poured. What looks like almost black concrete will lighten to a dark gray, and will have a combination of exposed and sand finished.

The back patios are poured. What looks like almost black concrete will lighten to a dark gray, and will have a combination of exposed and sand finished.